Project Report Airport – New Catering Centre Zurich

Simulation Catering Flughafen

Project report airport catering

Industry: Airport

Software: Plant Simulation

  • Illustration of the complete catering centre with new shuttle technology
  • Buffer and shuttle dimensioning
  • Determination of lorry requirements
  • Review and optimisation of process strategies
  • Determination of the required production capacities
  • Loading the current flight plans and equipment quantities
  • Implementation of the new shuttle technology
  • Mapping of the complete equipment handling process
  • Testing different flowlines
  • Safeguarding the new shuttle concept
  • Specifications for the production working time model
  • Specifications for lorry requirements

Other Projects

Simulationsprojekt für Nolte - SimPlan AG

nolte-Möbel GmbH & Co. KG: simulation production processes

fega und schmitt

Fega & Schmitt Electrical Retail – Warehouse Extension Heilsbronn

Motorradreifen

Automation of the quality inspection of motorcycle tires

Optimierung Produktion

Linde optimizes lift mast production with the help of simulation

AdobeStock_246772962_Pharma

Simulation of a pharmaceutical system